DEI Ruins EVERYTHING: Check Out How Woke 'Velma' Season 2 Updated Hex Girls...
Three Year Letterman HILARIOUSLY Mocks Protester Tackle in Epic Takedown
This Ain't It … Readers Sound Off on the Onion's First (GROSS) Article...
Donald Trump Dared to Speak Prompting a Pearl Clutching Daniel Dale Fact Check
'Jews Fight Back' - Jon Lovitz Spells it Out For Antisemites
Performative Northwestern Seder Roundly Decried for Taking Place on the Wrong Day
School Is in Session: Guy Learns the HARD WAY After Asking X Users...
AOC Visits Columbia 'Encampment' One Day After Released Video of Leader Calling for...
Wait, What? Julia Ioffe: College Presidents are TERRIFIED of the GOP. Shutting Down...
Incredible! Tornado Chaser Captures Stunning Footage of Nebraska Twister
We Regret to Inform You the 'Experts' Are at It Again: They Say...
Biden's INSANE Proposed Capital Gains Tax Would WRECK Economy
J.K. Rowling Takes Victory Lap and Applauds David Bell, Tavistock Gender Clinic Whistleblo...
You Don't Despise the Media Enough: CNN Omits MAJOR Bit of Info on...
Speaker Johnson Takes Charge of Academia's Radicalism Problem

DC Metro has spent $3.8 million and five years on two unfinished bike racks that were to be ready in 2015

It’s another episode of, “These are the people we want running health care?” WJLA in Washington, D.C. reported this week that the Washington Metropolitan Area Transit Authority, better known as Metro, has spent $3.8 million on two bike racks that aren’t even finished yet.

Advertisement

Sam Sweeney reports:

Metro has spent $3.8 million and taken five years to build two unfinished bike racks – at East Falls Church and Vienna Metro Stations.

WMATA originally budgeted $600,000 for each rack, but the price tag has soared to $1.9 million each.

The covered bike shelters will house 92 bikes, putting the price tag at more than $20,000 per bike. Future costs to finish the projects could raise that number even higher.

The projects were supposed to be completed in December of 2015 but remain unfinished in 2020.

Apparently there have been some problems with contractors, with Metro explaining, “Quality control issues with contractors can take time to sort out, but Metro determined it was more important to get the project done right rather than get it done quickly.”

Advertisement

Advertisement

It’s a bargain compared to California’s infamous high-speed train to nowhere.